Cenxi, Wuzhou City, is located at the junction of Guangdong and Guangxi in the southeast of Guangxi. It is rich in mineral resources, and is famous nationwide for its superior reserves and materials of granite, as well as the distinctive "Cenxi Red". Here, our equipment has also set up a fine gravel aggregate production line. Let's go and have a look.
On site of Cenxi Huangniuche Mining Area
The production line is located in Cenxi City, Wuzhou City, Guangxi Zhuang Autonomous Region, construction commenced in 2022. It is designed and constructed strictly in accordance with the green mine construction standards. The entire production line adopts SRHeavy crushing and screening equipment advanced in the industry, high-performance equipment, and reasonable production line process flow to ensure smooth connection in each link of crushing and screening. At the same time, we produce high-quality final gravel aggregate products that meet the production standards.
The entire production line is designed and constructed to reduce dust and noise, and is environmentally friendly. After the line is put into production, it will provide high-quality sand and gravel aggregate for the local building materials market to meet the needs of local urban development and construction.
Project file
Construction time: 2022
Project location: Cenxi City, Wuzhou City, Guangxi
Equipments: Vibrating Feeder SZ1870+Jaw Crusher SJ1500+Hydraulic Cone Crusher SG360S & SCH8000+Vibrating Screen 2SS3075+Vibrating Feeder SW1520
Project capacity: 500 t/h
Project feed: Granite
Feed size: ≤1000 mm
Finished products: 0-5 mm, 5-10 mm, 10-20 mm, 20-32 mm
Shaorui customization: Entire-line process, workflow and layout design; installation and commissioning; customized training for on-site operations
SG360S/SCH8000/SS series machine on site
The Cenxi project fully utilizes the top-down steps of the mining area and adopts a 3-stage crushing design, making reasonable use of space and reducing investment costs. With SRHeavy's unique process calculation software to accurately select equipment for each link, the performance advantages of each machine in the production line can be fully utilized. Thus, the entire production line is more efficient, energy-saving, and maximizes the quality of the final product.
The project has been officially put into production in April 2023. We will continue to track the operation of the project and present to you the latest trends in green mine construction.
Cenxi, Wuzhou City, is located at the junction of Guangdong and Guangxi in the southeast of Guangxi. It is rich in mineral resources, and is famous nationwide for its superior reserves and materials of granite, as well as the distinctive "Cenxi Red". Here, our equipment has also set up a fine gravel aggregate production line. Let's go and have a look.
On site of Cenxi Huangniuche Mining Area
The production line is located in Cenxi City, Wuzhou City, Guangxi Zhuang Autonomous Region, construction commenced in 2022. It is designed and constructed strictly in accordance with the green mine construction standards. The entire production line adopts SRHeavy crushing and screening equipment advanced in the industry, high-performance equipment, and reasonable production line process flow to ensure smooth connection in each link of crushing and screening. At the same time, we produce high-quality final gravel aggregate products that meet the production standards.
The entire production line is designed and constructed to reduce dust and noise, and is environmentally friendly. After the line is put into production, it will provide high-quality sand and gravel aggregate for the local building materials market to meet the needs of local urban development and construction.
Project file
Construction time: 2022
Project location: Cenxi City, Wuzhou City, Guangxi
Equipments: Vibrating Feeder SZ1870+Jaw Crusher SJ1500+Hydraulic Cone Crusher SG360S & SCH8000+Vibrating Screen 2SS3075+Vibrating Feeder SW1520
Project capacity: 500 t/h
Project feed: Granite
Feed size: ≤1000 mm
Finished products: 0-5 mm, 5-10 mm, 10-20 mm, 20-32 mm
Shaorui customization: Entire-line process, workflow and layout design; installation and commissioning; customized training for on-site operations
SG360S/SCH8000/SS series machine on site
The Cenxi project fully utilizes the top-down steps of the mining area and adopts a 3-stage crushing design, making reasonable use of space and reducing investment costs. With SRHeavy's unique process calculation software to accurately select equipment for each link, the performance advantages of each machine in the production line can be fully utilized. Thus, the entire production line is more efficient, energy-saving, and maximizes the quality of the final product.
The project has been officially put into production in April 2023. We will continue to track the operation of the project and present to you the latest trends in green mine construction.